Project Description
The U.S. 69 (18th Street) Bridge over the Kansas River in Kansas City, Kansas (KCK), is one of the few remaining deck truss bridges on the state highway system. Built in 1959, the bridge has undergone numerous rehabilitations over its 60-year life and needs a new design and complete replacement.
The project is moving forward with final design and will replace the bridge at its current location. The new bridge will use modern design standards, including new 10-foot-wide exterior shoulders and 6-foot-wide interior shoulders. It will also include visually appealing designs for the fencing over the railroad and the exterior concrete pattern. The pattern will be a stone pattern consistent with the Lewis and Clark Viaduct that connects KCK to Kansas City, Missouri, helping to reduce costs associated with maintenance and will provide a similar look and feel throughout the area. KDOT will be implementing additional improvements in the corridor to use a full closure of 18th Street and improve motorists’ driving experience.
These improvements will include:
- Roadway improvements along 18th Street just north and south of the river bridge.
- Bridge rehabilitation on the 18th Street bridges over Ruby Avenue, Metropolitan Avenue, KCT Railroad and Osage Avenue.
Project Location
Project Details
Project Name | 18th Street Bridge Replacement |
Project Number | KA-4881-02 |
Location | Over the Kansas River in Kansas City, Kansas (KCK) |
Scope | The bridge is nearing the end of its service life and any further rehabilitation beyond the repairs conducted in 2018 can no longer cost-effectively maintain this structure. The 18th Street bridge will have a complete bridge replacement, and KDOT will be implementing improvements to some of the adjacent bridges, roadway pavement, and roadside safety elements to make additional investments in the corridor and take advantage of the full closure. |
Approximate Length | N/A |
Project Timeline | Final design phase will conclude in 2024 with construction projected to begin in 2025. |
Construction Cost | N/A |
Project Schedule
The final design phase will conclude in 2024 with construction projected to begin in 2025. The bridge will be closed to traffic throughout the duration of construction. It is estimated that this full closure will last for two construction seasons or approximately 24 months. Alternative detour routes will include I-35, I-635 and I-70.
Public Meetings
Events
-
18th Street Bridge On-Demand Public Meeting
07/15/2022 - 07/29/2022
-
18th Street Bridge Public Information Open House