Centennial Bridge

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Description

As the only Missouri River crossing within a 38-mile area, Centennial Bridge is a vital resource for those who work and live in Leavenworth County, Kansas, and Platte County, Missouri. 

On average, more than 14,300 vehicles use the crossing every day. Unfortunately, the existing bridge is outdated and limited in its ability to transport people and goods. 

In 2011, KDOT began a multi-phase study to determine the future of the existing bridge. After conducting traffic, engineering, environmental, community engagement, and feasibility studies, KDOT determined the structure had exceeded its useful lifespan and that a new bridge was needed. 

Project Benefits:

  • The new bridge will not be tolled.
  • Improving flood resilience in the area.
  • Providing combined use pedestrian and bicycle accommodations.
  • Doubling the number of traffic lanes.
  • Resolving Missouri River navigation challenges.

Project Details

Project Name Route 92 Centennial Bridge 
Project Number KA-6016-01 
Location Leavenworth
Scope The new, four-lane Centennial Bridge will be constructed just to the north of the existing Missouri River crossing. 
Project Timeline The project is in the initial design phase, which includes surveying, environmental studies and permitting, preliminary roadway and structure engineering, and community engagement activities. 
Construction Cost $184.8 million

 

Anticipated Schedule

Centennial Bridge timeline graphic
Centennial Bridge timeline graphic
2021 December: Project Kick-off
2022

January: Surveying

April: Project Branding, Preliminary Engineering and  Design Activities Begin

May: Environmental (NEPA) Studies Begin

May - December: Key Stakeholder Meetings

2023

February: Public Meeting

August: Environmental (NEPA) Public Hearing

October: Field Review

2024 January: Begin Right-of-way (ROW) Activities
2025 Continue Right-of-way (ROW) Activities
2026

June: Design Complete

August: Bid Letting

 2027 Construction Begins*
 2029 Anticipated Construction Complete Date*

*Tentative date shown pending approval for construction.

Public Meetings

Events

More Events

Project Materials

Documents

Frequently Asked Questions

Expand/Contract Questions and Answers

Project Contacts

StaffPhoneEmail
Project Team, Centennial Bridge(913) 766-2198
Tholen, Delaney(785) 817-9365