Kansas Department Of Transportation
Home MenuCentennial Bridge
Project Description
As the only Missouri River crossing within a 38-mile area, Centennial Bridge is a vital resource for those who work and live in Leavenworth County, Kansas, and Platte County, Missouri.
On average, more than 14,300 vehicles use the crossing every day. Unfortunately, the existing bridge is outdated and limited in its ability to transport people and goods.
In 2011, KDOT began a multi-phase study to determine the future of the existing bridge. After conducting traffic, engineering, environmental, community engagement, and feasibility studies, KDOT determined the structure had exceeded its useful lifespan and that a new bridge was needed.
Project Benefits:
- The new bridge will not be tolled.
- Improving flood resilience in the area.
- Providing combined use pedestrian and bicycle accommodations.
- Doubling the number of traffic lanes.
- Resolving Missouri River navigation challenges.
Project Details
Project Name | Route 92 Centennial Bridge |
Project Number | KA-6016-01 |
Location | Leavenworth |
Scope | The new, four-lane Centennial Bridge will be constructed just to the north of the existing Missouri River crossing. |
Project Timeline | The project is in the initial design phase, which includes surveying, environmental studies and permitting, preliminary roadway and structure engineering, and community engagement activities. |
Construction Cost | $184.8 million |
Anticipated Schedule
2021 | December: Project Kick-off |
2022 |
January: Surveying April: Project Branding, Preliminary Engineering and Design Activities Begin May: Environmental (NEPA) Studies Begin May - December: Key Stakeholder Meetings |
2023 |
February: Public Meeting August: Environmental (NEPA) Public Hearing October: Field Review |
2024 | January: Begin Right-of-way (ROW) Activities |
2025 | Continue Right-of-way (ROW) Activities |
2026 |
June: Design Complete August: Bid Letting |
2027 | Construction Begins* |
2029 | Anticipated Construction Complete Date* |
*Tentative date shown pending approval for construction.
Public Meetings
Events
-
2023 NEPA Environmental Assessment Public Open House
08/29/2023 4:00 PM - 7:00 PM
-
Centennial Bridge Open House
02/21/2023 4:00 PM - 7:00 PM
Project Materials
Documents
Centennial Bridge Environmental Assessment
Route 92 Centennial Bridge Study
Environmental Assessment Open House News Release
Environmental Assessment Open House Fact Sheet
Environmental Assessment Open House Exhibits
Centennial Bridge Section 4(f) Evaluation
Centennial Bridge Open House News Release
Centennial Bridge Open House Fact Sheet
Centennial Bridge Open House Exhibits