I-135 Gold North Junction Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Description

Phase 2A

The first phase of the I-135 Gold Project included the replacement of the southbound I-135 ramp to southbound I-235, the replacement of the northbound I-135 loop ramp to southbound I-235 with a two-lane flyover ramp and the extension of the acceleration lane on the westbound K-254 ramp to southbound I-135. Work on the Gold Project Phase 2A began in April 2021 and was completed December 2023. 

Phase 2B

Gold Project Phase 2B includes a direct connection for eastbound K-96 traffic from northbound I-235 and new ramps for westbound traffic from K-96 at I-135. This phase of the project began in February 2023 with a completion date anticipated in late 2026.  

Project Details

Project Name I-135 Gold North Junction
Project Number KA-3232-01
Location I-235/I-135/K-254 interchange in north Wichita
Scope Interchange improvements
Approximate Length 2.82 miles 
Project Timeline Gold Project Phase 2A began in April 2021 and was completed December 2023. Gold Project Phase 2B began in February 2023 with a completion date in late-2026. 
Construction Cost

Gold Project Phase 2A – $36 million

Gold Project Phase 2B – Approximately $141 million