U.S. 83 is a critical rural freight corridor for western Kansas serving a variety of industries including agriculture, energy and livestock. Expanding transportation opportunities along the U.S. 83 corridor will help to improve economic productivity as well as the safe and efficient movement of agriculture products and other freight, benefiting everyone who travels on the corridor.

In September 2022, KDOT was awarded a $6.7 million Advanced Transportation and Congestion Management Technologies Deployment grant from the Federal Highway Administration to support the U.S. 83 Advanced Technology Project.

The Great Plains Rural Freight Technology Corridor Project (U.S. 83 Advanced Technology) will use technology aimed at improving safety and economic productivity along U.S. 83. The project limits extend approximately 131 miles, from the Thomas/Sheridan County line south to the Finney/Haskell County line.

Project Area Map

US 83 Advanced Technology Project Map

Project Details

Project Name U.S. 83 Advanced Technology Project
Project Number KA-6234-02 and KA-6234-01
Location U.S. 83 from south Finney County line, north to north Thomas County line. Involves Finney, Scott, Logan, and Thomas counties.
Scope Phase 1 includes the installation of approximately 90 miles of fiber optic cable along the corridor in preparation for phase 2 which will be the deployment of connected vehicle technology and an intelligent transportation system.
Approximate Length 131 miles
Project Timeline

2023 – 2025 (Phase 1 Design & Construction)

2023 – 2028 (Phase 2 Design, Development, Construction, & Testing)
Construction Cost $16.7 million

Project Schedule

Below is the project schedule that breaks down the tasks to be completed for phases 1 and 2. After the fiber optic cable is fully installed in early 2025, construction of the advanced technology field components will commence. Installation of the system technology is expected by the end of 2026. The technology will be fully operational at the beginning of 2027. Once operational, the system operations and performance will be monitored.

US 83 Project Schedule 

Note: Completion dates are subject to change

Concept of Operations

The Concept of Operations provides a detailed overview of the proposed improvements planned for the U.S. 83 corridor as part of this project. It reflects input received from project stakeholders and will be used to guide the project design and implementation process.

Project Materials

Documents

Frequently Asked Questions

Expand/Contract Questions and Answers

Project Contacts

StaffTitlePhoneEmail
Moreno, YazminDistrict 6 Public Information Officer(620) 765-7080
Mussman, LisaDistrict 3 Public Information Officer(785) 877-3315