The project includes the reconstruction of existing K-4 from the Smoky Hill River Bridge east about 7 miles to Kipp Road. The new alignment of K-4 will be offset to the north through a majority of the project limits to address several safety improvements including a flatter profile, improved intersection sight distance and the addition of paved shoulders. Traffic will be maintained during construction via existing K-4 and temporary pavement. County roads will be closed and detoured at times during construction. 

K-4 in Saline County is a highway modernization project currently in the Construction Pipeline for the IKE Program. The construction letting is planned for fiscal year 2025. 

Project Details

Project Name K-4 in Saline County
Project Number KA-3230-02
Location From about 2.3 miles east of the K-4/K-104 junction to about 0.3 miles east of the K-4/Kipp Road intersection 
Scope Reconstruction of offset alignment
Approximate Length 7.1 miles
Cost Estimate $27 million

Public Meetings

Events

More Events

Project Materials

Documents

Project Contacts

StaffTitlePhoneEmail
Deiter, JacobIKE Project Manager(816) 652-2600
Perez, AshleyDistrict 2 Public Information Officer(785) 515-6790